execution in due time

The regional correctional facility of North-Rhine Westphalia has found its new administrative location in Wuppertal. The former local court building was selected for its reference to its new purpose, in terms of content and history. Since December 2002, with the occupancy of the main building, the 37 legal authorities of North-Rhine Westphalia have been co-ordinated from this centre.

With the alteration of the former local court, the demolition of the associated penal institution and the construction of a new 5-storey building, a modern office and administration building was created in two stages of construction.

The connection of the listed former local court with the new building was a special architectural challenge. Owing to DU's involvement, the main development group of objects was completed with excellent results.

DU's particular aim was undercut the budget stipulated in the scope of the pre-planning. After the cost estimate and the final invoice for essential performances had been submitted, it began to show that this aim would certainly be achieved. Both building parts were completed and handed over to the user, in due time.

at a glance


Owner

Bau- und Liegenschaftsbetrieb NRW Düsseldorf

Architect

BLB

Location

Wuppertal

Gross surface area

approx. 5.592 m²

Gross volume

approx. 22.853 m³

Costs

approx. 6,8 Mio. € gross

Schedule

2001 - 2003

Services

Cost management
Cost planning
Monitoring of feasibility studies
Organisation management
Planning control
Process contol
Process control
Project accounting
Project control
Project handbook
Schedule planning
User demand program
Variance analysis